MAIN PAGEMODIS INFOINSTRUMENT OPSWeekly ReportsMODIS HistoryCALIBRATIONL1B PRODUCT INFO
|
MODIS IOT Terra Weekly Report
Mission Operations Days: 2001/104 to 2001/110
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Terra (AM-1) is in Normal Ops Mode MODIS is in Science Mode - B Side |
||
| Component | State(s) | Comment |
|---|---|---|
| Blackbody | A Off; B On (290 K) | Nominal |
| Calibration Electronics | A Off; B On | Nominal |
| Control Processor | A Off; B On | Nominal |
| Nadir Door | Unlatched, Open | Nominal |
| Space View Door | Unlatched, Open | Nominal |
| Solar Diffuser Door | Unlatched, Closed | Nominal |
| FDDI Formatter | A Off; B On | Nominal |
| FDDI Port | A On; B Off | Nominal |
| FIFO Memory | #1 & #2 Off; #3 & #4 On | Nominal |
| Format Processor | A Off; B On | Nominal |
| Power Supplies | #1 Off; #2 On | Nominal |
| PV VIS FPA | A Off; B On | Nominal |
| PV NIR FPA | A Off; B On | Nominal |
| PV SMIR FPA | A Off; B On | Nominal |
| PV LWIR FPA | A Off; B On | Nominal |
| PC LWIR FPA | A Off; B On | Nominal |
| RC Outgas Heaters | All Off (CS, IS, OS) | Nominal |
| RC LWIR FPA Heater | On (83 K) | Nominal |
| RC SMIR FPA Heater | Off | Nominal |
| Scan Assembly | A Off; B On | Nominal |
| SDSM | A Off; B Off | Nominal |
| SRCA | A Off; B Off | Nominal |
| PS1 Survival Heater | Enabled | Nominal |
| PS2 Survival Heater | Enabled | Nominal |
| Timing Generator | A Off; B On | Nominal |
| Flight Software | Rev BD + 1 set of patches
| Nominal |
| Inhibit Ids Set | None | Nominal |
| TMONs Enabled | 68 | Nominal |
2001/103 21:00:00 ATC OA-26: B-side Set Blackbody Temperature to 270K
2001/104 15:00:00 ATC OA-26: B-side Set Blackbody Temperature to 280K
2001/104 19:00:00 ATC OA-26: B-side Set Blackbody Temperature to 285K
2001/104 22:00:00 ATC OA-26: B-side Set Blackbody Temperature to 290K
2001/105 02:00:00 ATC OA-26: B-side Set Blackbody Temperature to 295K
2001/105 02:00:30 ATC OA-26: B-side Set Blackbody Heater duty cycle to FULL
2001/105 04:00:00 ATC OA-26: B-side Set Blackbody Temperature to 300K
2001/105 06:00:00 ATC OA-26: B-side Set Blackbody Temperature to 315K
2001/105 09:00:00 ATC OA-26: B-side Set Blackbody Temperature to 270K
2001/105 09:00:30 ATC OA-26: B-side Set Blackbody Heater duty cycle to THIRD
2001/106 05:00:00 ATC OA-26: B-side Set Blackbody Temperature to 290K
None
Wednesday, April 18, 2001
2001/108 21:44:03 ATC OA16: SDSM SCREENED
2001/108 23:22:55 ATC OA15: SDSM OPEN
2001/109 01:13:28 – 01:15:59 ATC OA27: PV ECAL
2001/109 01:16:53 – 01:21:24 ATC OA28: PC ECAL
None
None
None
Saturday, April 21, 2001None
Sunday, April 22, 2001None
Monday, April 23, 2001None
Tuesday, April 24, 2001None
Wednesday, April 25, 2001None
Thursday, April 26, 2001None
Friday, April 27, 2001None
In addition:A new set of SRCA cross-talk measurements are being planned for later this month and will use memory load patches to change the size of the SRCA sector from 10 frames to 55 frames in the same manner as was done on March 2, 2001.
Again, there will be no MODIS roll maneuver in May because the roll angle would have been too great. The next attempt for a roll maneuver will be June.
There is a Drag makeup maneuver being planned tentatively for the first week in May.
None.
MODIS is in Science Mode on the B-side with the SVD and NAD open, operating with the Formatter Resolution Flight Software Patches (FRFSP).
Nothing new to report.
None.
SRCA 10W Lamp #1: 185.0 of 500 hours
SRCA 10W Lamp #2: 142.4 of 500 hours
SRCA 10W Lamp #3: 151.6 of 500 hours
SRCA 10W Lamp #4: 61.5 of 500 hours
SRCA 1W Lamp #1: 557.3 of 4000 hours
SRCA 1W Lamp #2: 276.3 of 4000 hours
Solar Diffuser Door: 1591 of 3022 Movements
Nadir Aperture Door: 532 of 1316 Movements
Space View Door: 437 of 1316 Movements
Email the MODIS IOT
to report any problem with the MODIS IOT Web Pages.
Email the MCST Webmaster
to report any problem with the MCST Web Pages.
Email the MCST Helpdesk
to ask a question about Level 1B usage, algorithms or software.
Last Update: Friday, 21-Feb-2003 14:42:17 EST